When you need planning approval
A granny flat that meets all the R-Codes' standard ("deemed-to-comply") rules usually doesn't need planning approval. You need it when your design breaks one of them, for example:
- It's bigger than 70 m².
- It's too close to a boundary or sits in the street setback.
- There's no extra parking bay, and you're not near high-frequency transport.
- It overlooks neighbours from an upper floor or deck.
- It's on land with a local plan, heritage listing or rural zoning that adds rules.
Breaking a standard rule doesn't mean a "no". The council checks your design against the R-Codes' design principles instead, which are more flexible.
Step by step
| Step | What to do |
|---|---|
| 1. Find the problem | List each rule your design breaks. Some councils offer a paid check to tell you. |
| 2. Explain why it works | For each one, write how your design still meets the design principle, such as no overshadowing or privacy screening. |
| 3. Lodge the application | Lodge online with the form, plans and fee. A planning fee for work under $50,000 is $147 in 2025/26. Bigger jobs cost more. |
| 4. Neighbour comment | If the change affects neighbours, the council may ask them for comment. |
| 5. Decision | Councils have 60 days, or 90 days with neighbour comment. Approval may come with conditions. |
| 6. Building permit | Only then apply for the building permit, meeting any conditions. |
If the council asks for more information, reply quickly. The City of Gosnells, for example, gives you 21 days or it may refuse. Applying after you've already built costs more: the City of Joondalup adds a penalty of twice the fee.
If it's bigger than 70 m²
Over 70 m² is outside the granny flat rules, so the council may assess it as a second house instead. That brings in lot size and density rules, so ask your council early. Councils vary.
Check if you can skip planning approval, use the granny flat size calculator, or read the full granny flat approval process.